The Build Process

At a glance: Once land, finance, detailed designs and statutory approvals are in place, a HebHomes build typically runs over 6–8 months on site. The key stages are:

  • Appoint Contract Administrator & inform planners
  • Clear site, set out & dig trenches
  • Build foundations, drainage & slab
  • Erect kit to wind & weathertight
  • Finish roof
  • First fix (joinery, plumbing, electrics, insulation, plasterboard)
  • Second fix (kitchen, bathrooms, heating/ventilation, finishes)
  • External finishes & landscaping
  • Handover, Completion Certificate & occupation
  • Defect period & final retention

Explore our webinars for a step-by-step view of the process: Company Webinars, Turnkey Service, Webinar Playlist.

Appoint Contract Administrator & Inform Planners

We recommend appointing a Contract Administrator (architect, QS or other qualified professional) when you go on site. They certify monthly valuations, manage changes, and protect your interests. Before work begins, check and discharge planning conditions and inform the planning department of your start date.

Clear Site

Install temporary access and clear the plot. With a Supply Only package, this is carried out by your main contractor.

Set Out & Dig Trenches

The house position and levels are set out; your engineer can check accuracy to avoid boundary/height issues. Trenches are then excavated for foundations.

Build Foundations

Concrete strip foundations are poured to the engineer’s drawings. Underbuild blockwork is taken to DPC, then hardcore, sand blinding and the concrete slab are installed. Drainage/sewerage is typically installed at this stage. A HebHomes representative inspects foundations to confirm suitability before kit delivery.

Erect to ‘Wind & Weathertight’

The kit arrives and erection begins. A typical four-person team erects most homes in ~7 working days (size/complexity/weather dependent). Works include fixing sole plates; erecting SIP/CPS walls, lintels and joists; installing floors, ridge and roof panels; internal vapour control; external membranes; non-loadbearing partitions and windows. The structure is now secure and weather-protected, but full sealing depends on exterior claddings and sealants.

Finish the Roof

While scaffolding is up, complete battening and roof coverings (profiled metal or slate), flashings and roof lights.

First Fix: Joinery, Plumbing & Electrics

Internal battening/framing proceeds; electricians run cabling; plumbers install pipework and underfloor heating; ventilation ducting is set; sound insulation is fitted. Plasterboard follows (insulated boards to external walls; fire-resistant behind stoves; moisture-resistant in bathrooms; thicker boards to ceilings for acoustics).

Second Fix

After taping/filling or plastering, finishes begin: hanging doors; skirtings and architraves; installing sanitaryware and connecting systems; fitting kitchen; laying floors; tiling; connecting heat pump and MVHR; final electrical fit-off.

External Finish

Timber cladding or outer leaf/render, guttering and final drainage connections progress in parallel with internal works (rendering is weather-dependent).

Finishing Touches

Decoration, landscaping and drive finishes (gravel, tarmac, planting). The house is almost ready for occupation.

Handover

The Contract Administrator certifies Practical Completion. Typically, valuations occur every four weeks and 5% retention is held through the build. At PC, keys are handed over, you assume insurance duties, and (subject to locale) you may occupy once the Completion Certificate is issued by Building Control.

Defects Period

During the (usually 12-month) defect period, record any snags/latent defects to be made good. The final retention is released once defects are rectified. If you chose our turnkey route, HebHomes organises NHBC/BOPAS warranties and coordinates Completion Certificate; otherwise your administrator arranges certification and warranty.



Common Questions

How long does a HebHomes build take?
Most on-site programmes run 6–8 months, depending on size, complexity and weather. Kit erection is rapid (~7 days for many homes) but follow-on trades and finishes take longer.
What does ‘wind & weathertight’ mean?
Structure, roof, membranes and windows are installed so the building is secure and largely weather-tight. Full sealing is achieved after cladding and external sealants are complete.
What does a Contract Administrator do?
They administer the contract, certify valuations, manage change control, check compliance/quality, hold retention and protect your payment position.
What’s included in first fix vs second fix?
First fix: framing/battens, wiring, pipework, ventilation ducting, insulation, plasterboard. Second fix: doors/skirts/architraves, kitchen, bathrooms, tiling/flooring, final electrical fit-off, heating/ventilation commissioning.
What inspections happen before the kit arrives?
Your engineer designs and inspects foundations; Building Control may inspect stages; HebHomes checks foundation suitability and access/lay-down areas for safe erection and telehandler movements.
When can I move in?
After Practical Completion and once Building Control issues a Completion Certificate (region-dependent). You then assume insurance responsibilities.
How do valuations and retention work?
Valuations are typically every four weeks. A 5% retention is held during the build; half is released at Practical Completion and the remainder after the defect period once snags are resolved.
Are HebHomes kits mortgageable?
Yes. SIP and CPS homes are mortgageable with an accepted 10-year structural warranty. HebHomes’ CPS system is BOPAS-accredited, which reassures lenders using modern methods of construction.
Where can I learn more?
Watch our webinars: Company Webinars, Turnkey Service, or browse our YouTube playlist.

Action Points

Ready to Begin?

Whether you're exploring ideas or ready to plan, we're here to help

Discuss Your Project
  • Herald Property Awards
  • BM Trada
  • Rias
  • Bopas